ASB Water Infitration Remediation
General Description. The Administrative Services Building Water Infiltration project will address various water infiltration issues, including the following:
- The existing EPDM roof on the 1960’s addition will be replaced.
- Water infiltration at two foundation areas will be remediated.
Design Team. The design and construction administration will be provided by Faridy Veisz Fraytak.
Current Status. The Design Development documents have been submitted by Faridy Veisz Fraytak. The Construction Documents phase will begin in late July 2008.