October 19, 2004:
 |
Attendance: Nick Vertucci, Eric
Wojcik, Stephen Lewis, Nick Terzulli, Dr. Kurland,
Dr. Limberis |
 |
Motors
delivered....delicious. |
 |
Motor
drivers delivered |
 |
Chassis
discussion |
 |
Talk to Alex
M. about cutting wood for maze |
 |
Begin making
tables for SP1 presentations |
 |
Algorithms
are continuing |
 |
Team meeting
set for Wednesday, October 27th at 3pm in AR-148 |
 |
Finalize
IEEE project proposal (2 pages) |
October 12, 2004:
 |
Attendance: Nick Vertucci, Eric
Wojcik, Stephen Lewis, Nick Terzulli, Dr. Kurland,
Dr. Limberis |
 |
Motor
selected from Jameco; ready to order. |
 |
Sensors
delivered |
 |
Preliminary
coding underway |
1.Correction
algorithm
 |
Room access
memo signed |
 |
Begin
voltage regulator research |
 |
Begin
project proposal for IEEE |
 |
Check with
last year’s team about trip funding |
 |
Check if
company’s would like logo on our webpage |
October 5, 2004:
 |
Attendance: Nick Vertucci, Eric
Wojcik, Stephen Lewis, Nick Terzulli, Dr. Kurland,
Dr. Limberis |
 |
Microcontrollers delivered and tested. Need new power adaptor. |
 |
Sensors
ordered. |
 |
Motors: |
1.Difficult
time finding right ones
2.Talk to Dave
Ciotti and Mike Mensch
3.Meet this
weekend to finalize search
 |
Batteries
decided on. Check nominal discharge characteristics. |
 |
Website
account finalized |
 |
Room access
granted |
 |
Approach
Alex M. regarding maze construction help |
September 28th,
2004:
 |
Attendance: Nick Vertucci, Eric
Wojcik, Stephen Lewis, Nick Terzulli, Dr. Kurland,
Dr. Limberis, Ben A. |
 |
Motors: (NT) |
1.Difficulty in finding motor drivers
2.Lean towards fabricating our own motor driver
3.Talk to motor manufacturers and suppliers.
 |
IEEE: |
1.Proposal tentatively set for the end of October.
2.
Acknowledge IEEE’s generosity
from last year.
 |
Sensors –
Settled on sensors. Contacting company about price break. (NV) |
 |
Microcontrollers & Coding: (EW) |
1.MAVRICs ordered on 9/27/2004
2.
Began Lee-Moore algorithm
coding in C.
 |
Batteries –
shy away from lithium-ion rechargeables due to availability/price of
charger. (SL) |
 |
Create memo
for continued team lab use. |
 |
Team meeting
set for Wednesday, September 29th @ 6:30pm in General Lab for
editing of progress report PowerPoint. |
September 21st,
2004:
 |
Attendance: Nick Vertucci, Eric
Wojcik, Stephen Lewis, Nick Terzulli, Dr. Kurland,
Dr. Limberis, Ben A. |
 |
Gantt chart
review – update design fields. (SL) |
 |
IEEE design
proposal – Have short project proposal ready by mid-October for presentation
to IEEE funding board. |
 |
Ask local
IEEE chapter about possible funding. (SL) |
 |
Request loft
in Room 123 be set aside for Micro-Mouse team. |
 |
Microcontroller – Settled on MAVRIC microcontroller. Will buy 2 depending
on availability of funds. (EW) |
 |
Sensor
Comparison: (NV) |
1. Agree on threshold sensor in front of mouse to stop from hitting wall.
2.
35-50 mA draw on sensors so
far.
3.
10 degree angle of deflection
desirable.
 |
Motor
selection – motors are so far in the $10-$20 range. (NT) |
 |
Begin
drawing up budget. |
 |
Batteries
– Rechargeable vs. Disposable. Create cost chart. (SL) |
 |
Went over
Realistic Constraints paper for SP I class |
September 14th, 2004:
 |
Attendance: Nick Vertucci, Eric
Wojcik, Stephen Lewis, Nick Terzulli, Dr. Kurland |
 |
Talk to Dr.
Limberis about hosting this year’s competition (NV) |
 |
Decided on
Top-Down threshold sensor array placement |
 |
Gantt chart
tasks (SL) |
1.
Design completion
a. Mechanical
Drawings (NT)
2.
Parts selection
a.
Motor Selection (NT)
b. Sensor Selection
– 6 x threshold, 1 x Distance (NV)
c. Battery
Selection (SL)
 |
Begin C code modules (EW) |
 |
Order Parts (deadline: end Oct/ beginning
Nov) |
 |
Begin Construction by end of semester |
September 9th, 2004:
 |
Attendance: Nick Vertucci, Eric
Wojcik, Stephen Lewis, Nick Terzulli, Dr. Kurland |
 |
Future meeting scheduled for
Tuesdays at 11:30am. |
 |
Purposes of meetings: 1)
Communication amongst team members and 2) To help Stay on schedule |
 |
Dr. Kurland advised team members
of the grading criteria |
 |
Money available for project
≈ $1,000.00 |
 |
Begin work
on Gantt charts in order to plan out semester's work |
 |
Primary
design consideration: Placement of sensors |
 |
Nick T. to
get copy of last year's Micro-Mouse paper |
 |
Nick V. to
get website up and running |
 |
Eric to
study last year's algorithms and convert to C |
 |
Ask Mary to
put out email asking for undergraduates on team |
 |
Set goal of
First Place at 2005 Micro-Mouse competition |
|