Mechanical:
Prior to the beginning of Spring break all necessary components for the
new frame had been ordered and where scheduled to arrive during the
break so that construction of the new frame could be completed upon the
team's return to school.
Software:
An interface for the Canon digital camera has been completed, which
allows Matlab to operate the camera autonomously. Work has also
been done on building an image database in order to aid in the image
processing developement.
Hardware:
The new uPatch100 GPS unit, generously donated by Fastrax, has been successfully wired
up and tested. The GPS code still needs to be adapted in order to
operate successfully with the new unit.
Fundraising:
The "New Jersey Engineering" T-shirts are once again available for
purchase. Shirts are $10 each and various sizes are still
available, please ask one of the team members about them if you are
interested in purchasing one.
|